removed from battery. Additionally, when battery is on equalize,
rectifier output voltage must be reduced by 2.33 volts for each
cell removed. UPS alarms shall be adjusted as necessary. Notify
Contracting Officer immediately if it becomes necessary to remove
any cell. Defective cells should be replaced as soon as possible.
Contractor, via Contracting Officer, shall contact NFESC ECDet,
Code 65 for assistance.
3.4
FIELD QUALITY CONTROL
Contractor shall be on-site during UPS system testing. Provide equipment,
test instruments, power, load bank, materials and labor required for tests.
Contracting Officer will witness all tests and the tests shall be subject
to his approval. Defects resulting from improper handling or installation
shall be corrected by the Contractor and retested at no additional cost to
the Government. Defects resulting from non-Contractor furnished equipment
failure shall be repaired by equipment manufacturer. Contracting Officer
will make final decisions as to whether a failure was due to improper
installation or defective non-Contractor furnished equipment.
3.4.1
UPS Unit Performance Test
Upon completion of battery activation procedures and as directed by
Contracting Officer, Contractor shall connect load bank to UPS output.
Load bank required shall be determined by the following:
UPS KVA RATING
X
0.8
=
KW of LOAD BANK
Performance test is to be run under the supervision of the UPS technical
representative. UPS unit shall be operated under full load for a minimum
of one hour. Contractor shall be required to operate feeder and bypass
power feeder breakers during testing of the UPS.
[3.4.1.1
**************************************************************************
NOTE: Delete this paragraph if an emergency
generator is not required.
**************************************************************************
Test UPS to observe operation with emergency generator service. UPS
technical representative shall verify UPS battery current limiting feature
functions properly.
]3.4.2
Battery Performance Test (Constant KW)
Furnish all labor, material and test equipment necessary to conduct
performance test under the direction of UPS technical representative.
The
following shall be accomplished:
a.
Install a calibrated voltmeter across the battery terminals to
measure voltage, and install a calibrated voltmeter across the UPS
DC shunt to read charging current. UPS technical representative
will advise connection to DC shunt.
b.
Record temperature of pilot cells in battery immediately prior to
start of discharge performance test.
c.
Read and record total battery voltage and battery current at start
SECTION 16262N
Page 18