percent efficiency. Select the appropriate
concentration reduction value for the field tests.
**************************************************************************
After installation the filtration system shall be field tested for leaks
using a mechanical test method. The system shall also be tested for leaks
installation and shall be performed by an independent testing agency in
accordance with ASME N-510-1. The test agency shall be certified in
accordance with ASME NQA-1 or have demonstrated previous experience with
similar systems as approved by the Contracting Officer. [The carbon
adsorber system housing and carbon adsorber will be challenged with
refrigerant vapor R-134a or equivalent with the downstream concentration
not to exceed [0.001] [0.0001] times the upstream concentration.] [The
HEPA filter DOP aerosol penetration will be less than 0.03 percent.]
3.8
FIELD TRAINING
**************************************************************************
NOTE: The number of hours of instruction should be
determined based on the number and complexity of the
systems specified.
**************************************************************************
The Contractor shall conduct a training course for operating and
maintenance personnel as designated by the Contracting Officer. Training
shall be provided for a period of [_____] hours of normal working time and
shall start after the system is functionally complete but prior to the
performance tests. The field instruction shall cover all of the items
contained in the approved Operating and Maintenance Instructions and the
Filtration Unit Manuals.
-- End of Section --
SECTION 15860A
Page 21