3.6.3.2
Protection
The Contractor shall be responsible for protecting boiler and components
from damage after installation until Government takes custody. After
installation, touchup paint shall be provided to damaged areas on shop and
finish-coated surfaces of the equipment. Surfaces shall be free of rust,
scale and foreign substances before application of touchup paint. The
touchup paint shall be equivalent to the shop and/or finish paint.
3.6.3.3
Adjusting, Inspecting, and Cleaning
a.
Contractor shall thoroughly clean inside of boiler by performing
boil-out, flushing and cleaning in accordance with manufacturer's
instruction prior to startup.
b.
Final adjustment to boiler shall be in accordance with
manufacturer's recommendations, but not less than following:
1.
Verify lubrication of moving parts.
2.
Verify fan rotation direction.
3.
Adjust water level control for proper operating level.
4.
Adjust firing rate control.
5.
Confirm operation of safety devices.
6.
Adjust controls and verify operation.
3.6.3.4
Field Quality Control.
a.
Contractor shall provide trained field representative to supervise
installation of boiler and its components. Field representative
shall inspect alignment and balancing of rotating and moving
parts. After completion of installation, Contractor shall provide
services of factory-trained field representative to start and
adjust boiler.
b.
Manufacturer shall provide trained field representative for final
inspection of boiler for proper installation, alignment and
c.
Contractor shall coordinate with other representatives on startup
of other items and building services as required.
d.
Contractor's representative shall be available to instruct and
train Government personnel for not less than two (2)days after
3.6.4
Gaseous Emissions Monitor
Extractive or in-situ gaseous emissions monitor shall be provided.
Combination of extractive and in-situ monitors is not acceptable. Gas
monitors shall include automatic calibration checks. Alarm horn and
annunciator shall be provided to alarm when any monitored parameter is out
of range or gaseous emission monitor malfunctions. Surfaces exposed to
corrosive gas of boiler shall be constructed of noncorrosive materials such
as 316 SS, Teflon or Hastalloy.
SECTION 15561A