3.2.5.15
Plant Acceptance Operation
After satisfactory completion of tests specified, operate the complete
subsystems for a period of 30 continuous 24 hour operational days prior to
final acceptance by the Government. Furnish labor, chemicals, test
equipment and apparatus; the Government will furnish fuel, electricity and
water. During this 30 day period, furnish readily available, the services
of qualified representatives from manufacturers of plant components and
systems for the purpose of additional operational assistance, component and
system adjustment and repairs. Government personnel will observe
Contractor's operational procedures. The Contractor's representatives
shall be prepared to answer pertinent questions from the Government, about
the plant operation.
3.2.6
Manufacturer's Field Services
3.2.6.1
Erection/Installation Supervisors and Service Engineers
a.
Boiler: Furnish the services of a competent supervisor who is in
the direct employ of the boiler manufacturer. This supervisor
shall remain on the construction site the full 8 hours per day, 5
days per week, or the same hours, that the boiler installation
takes place. This supervisor shall be responsible for the
complete steam generating unit, including the steam generator,
forced draft fan, burner and other related work, such as
refractory, or insulation regardless of whether the forced draft
fan, burner or the other related items of work are furnished by
manufacturers other than the boiler manufacturer.
b.
Forced Draft Fans: The Contractor shall furnish a company service
engineer to advise on the erection or installation of fans and
related equipment.
c.
Service Engineers: Services of the manufacturing companies'
service engineers and the system suppliers' service engineers
shall be provided by the Contractor to advise during erection and
installation of other systems and equipment such as air
condensate pumps, water treatment equipment, chemical feed pumps,
deaerating feedwater heater and stacks.
3.2.6.2
Boiler and System Representatives
a.
Furnish factory trained engineers or technicians who are
representatives of the boiler manufacturer and system suppliers to
b.
Furnish the services of a Boiler Inspector who is qualified and
certified as such by the National Board of Boiler and Pressure
Vessel Inspectors and who is presently employed full time by a
firm, such as Hartford Steam Boiler Inspection and Insurance
Company, which has a business of inspecting boilers.
3.2.6.3
Instruction to Government Personnel
In accordance with the provisions of Section 15050N BASIC MECHANICAL
MATERIALS AND METHODS, supervisors and service engineers shall provide
instruction for the Government's operators in the operation and maintenance
SECTION 15511N
Page 93