3.2.7
Manufacturer's Field Services
3.2.7.1
Erection/Installation Supervisors and Service Engineers
a.
Boiler: Furnish the services of a competent supervisor who is in
the direct employ of the boiler manufacturer. This supervisor
shall remain on the construction site the full 8 hours per day, 5
days per week, or the same hours as the boiler erectors are on the
job. This supervisor shall be responsible for the complete steam
generating unit, including the steam generator, stoker, fans and
related work, such as refractory, or insulation regardless of
whether the stoker, fans or other related items of work are
furnished by manufacturers other than the boiler manufacturer.
b.
Stoker: Furnish a competent erection supervisor
for the
equipment furnished by the stoker manufacturer.
c.
Fans: Furnish a company service engineer to advise on the
erection or installation of fans and related equipment.
d.
Service Engineers: Furnish services of the manufacturing
companies' service engineers and the system suppliers' service
engineers to advise during erection and installation of other
feedwater pumps, fuel oil pumps, condensate pumps, water treatment
equipment, chemical feed pumps, deaerating feedwater heater and
stacks.
3.2.7.2
Boiler and System Representatives
Furnish factory trained engineers or technicians who are representatives of
the boiler manufacturer and system supplier to supervise testing of the
a.
Furnish the services of a Boiler Inspector who is qualified and
certified as such by the National Board of Boiler and Pressure
Vessel Inspectors and who is presently employed full time by a
firm, such as Hartford Steam Boiler Inspection and Insurance
Company, which has a business of inspecting boilers.
3.2.7.3
Instruction to Government Personnel
Supervisors and service engineers shall provide instruction for the
Government's operators in the operation and maintenance of the equipment
furnished under this section. The minimum number of hours provided shall
be as follows:
Equipment
Operation Instruction
Maintenance
Instruction
Boiler and auxiliaries
40
hours
16
hours
Stoker
40
hours
16
hours
F.D. and I.D. fans
16
hours
16
hours
Coal handling system
16
hours
32
hours
Ash handling system
24
hours
8
hours
8
hours
16
hours
Boiler feedwater pumps
8
hours
8
hours
Miscellaneous equipment
16
hours
16
hours