3.2.6.7
Temporary Waste Steam Connection
When necessary to obtain sufficient load for these tests, provide a
temporary steam line at a point outside of building. Provide necessary
pipe, fittings, supports, anchors and appurtenances including a field
fabricated silencer as directed by the Contracting Officer. Remove
temporary piping and silencer after tests have been satisfactorily
completed.
3.2.6.8
Conduct tests as necessary to determine compliance with the applicable UL
Safety Standards. The presence of the applicable Underwriters' label may
be accepted as evidence of compliance in this respect when equipment is
manufacturer's standard commercial product.
a.
Meet test requirements of UL 726.
b.
Oil Burners:
Meet test requirements of UL 296.
3.2.6.9
Plant Acceptance Operation
**************************************************************************
NOTE: Include bracketed portion when project is for
coal fired installation with flue gas
desulfurization system.
**************************************************************************
After satisfactory completion of tests specified, operate complete plant
subsystems for a period of 30 continuous 24 hour operational days prior to
final acceptance by the Government. Furnish labor, chemicals, test
equipment and apparatus; the Government will furnish fuel, electricity and
water. During this 30 day period, furnish readily available, services of
qualified representatives from manufacturers of each plant component and
system for the purpose of additional operational assistance, component and
system adjustment and repairs. Government personnel will observe
Contractor's operational procedures. The Contractor's representatives
shall be prepared to answer pertinent questions from the Government about
the plant operation.
3.2.6.10
NAVFACENGCOM Acceptance
shall be completed prior to requesting an acceptance inspection by a Naval
Facilities Engineering Command (NAVFACENGCOM) Boiler Inspector. The
Contracting Officer, upon receipt of 14 calendar days advance notice from
the Contractor, shall request that the boiler plant by a qualified
NAVFACENGCOM Boiler Inspector. Contractor shall perform final operational
NAVFACENGCOM Boiler Inspector, at the inspector's discretion. The
NAVFACENGCOM Boiler inspector shall receive copies, and review the results,
of all pertinent operational test reports before approving acceptance of
the boiler plant by the Government.