complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Gas Piping System
Drawings showing location, size and all branches of pipeline;
location of all required shutoff valves; and instructions
necessary for the installation of connectors and supports.
SD-03 Product Data
Welding
Qualified procedures and a list of names and identification
symbols of qualified welders and welding operators.
Gas Piping System
all related system components
SD-06 Test Reports
Testing
Pressure Tests
Pressure Tests for Liquified Petroleum Gas
Test With Gas
Test reports in booklet form tabulating test and measurements