System surge analysis; G]
SD-06 Test Reports
**************************************************************************
NOTE: Consult with the Division Fire Protection
Engineer before specifying 2-wire smoke detectors as
a Contractor option. 2-wire detectors must be
carefully matched to the control panel by the
manufacturer, and are not universally
interchangeable between systems for maintenance
purposes.
**************************************************************************
Open-area (Spot-Type) 2-wire smoke detectors; G
Submit copies of UL listing or FM approval data showing
compatibility of the smoke detector model being provided with the
control panel being provided, if 2-wire detectors are proposed for
use.
Preliminary tests; G
Acceptance tests; G
Submit for all inspections and tests specified under paragraph
entitled "Field Quality Control."
Hydrostatic testing of the diaphragm pressure proportioning tanks;
G
SD-07 Certificates
Qualifications of installer; G
Submit installers qualifications as required under paragraph
entitled Qualifications of Installer."
AFFF containment and disposal plan; G
Year 2000 (Y2K) Compliance Warranty
Backflow preventers; G
SD-10 Operation and Maintenance Data
[Deluge] [Pre-action] valves, Data Package 3; G
Proportioning equipment, Data Package 3; G
Control panel, Data Package 3; G
AFFF concentrate storage tanks, Data Package 3; G
SECTION 13956N