(1)
The systems manufacturer's technical representative
(2) Marked-up red line drawings of the system as actually
installed
(3)
(4)
(5)
Complete program printout including input/output addresses
The final tests shall be witnessed by the [[____] Division] [EFA [____]],
Naval Facilities Engineering Command, Fire Protection Engineer. At this
time, any and all required tests shall be repeated at their discretion.
Following acceptance of the system, as-built drawings and O&M manuals shall
be delivered to the Contracting Officer for review and acceptance. In
existing buildings, the transfer of devices from the existing system to the
new system and the permission to begin demolition of the old fire alarm
system will not be permitted until the as-built drawings and O&M manuals
are received.
3.6.2
Minimum System Tests
Test the system in accordance with the procedures outlined in NFPA 72.
The
required tests are as follows:
a.
Verify the absence of unwanted voltages between circuit conductors
and ground. The tests shall be accomplished at the preliminary
test with results available at the final system test.
b.
detailed in the manufacturer's O&M manual.
c.
Test each initiating and indicating device and circuit for proper
operation and response at the control unit. Smoke sensors shall
be tested in accordance with manufacturer's recommended calibrated
test method. Testing of duct smoke detectors shall comply with
the requirements of NFPA 72.
d.
Test the system for specified functions in accordance with the
contract drawings and specifications and the manufacturer's O&M
manual.
e.
Test both primary power and secondary power. Verify, by test, the
secondary power system is capable of operating the system for the
time period and in the manner specified.
f.
Determine that the system is operable under trouble conditions as
specified.
g.
Visually inspect wiring.
h.
Test the battery charger and batteries.
i.
Verify that software control and data files have been entered or
programmed into the FACP. Hard copy records of the software shall
be provided to the Contracting Officer.
SECTION 13855N
Page 40