equipment specified, not later than [3] [_____] months prior to
the date of beneficial occupancy. Data shall include a complete
list of parts and supplies with the current unit prices and source
of supply and a list of the parts recommended by the manufacturer
to be replaced after [1] [_____] year of service.
Technical Data and Computer Software[; G][; G, [_____]]
Technical data which relates to computer software.
Training
and training data, furnished in manual format, for the training
courses. The operations training shall familiarize designated
government personnel with proper operation of the fire alarm
system. The maintenance training course shall provide the
designated government personnel adequate knowledge required to
diagnose, repair, maintain, and expand functions inherent to the
system.
Testing
Detailed test procedures, prepared and signed by a Registered
Professional Engineer or a NICET Level [3] [4] Fire Alarm
Technician, for the fire detection and alarm system [60] [_____]
days prior to performing system tests.
SD-06 Test Reports
Testing
Test reports, in booklet form, showing field tests performed to
prove compliance with the specified performance criteria, upon
completion and testing of the installed system. Each test report
shall document readings, test results and indicate the final
position of controls. The Contractor shall include the NFPA 72
Certificate of Completion and NFPA 72 Inspection and Testing Form,
with the appropriate test reports.
SD-07 Certificates
Equipment
Certified copies of current approvals or listings issued by an
independent test lab if not listed by UL, FM or other nationally
recognized testing laboratory, showing compliance with specified
NFPA standards.
Qualifications
Proof of qualifications for required personnel. The installer
shall submit proof of experience for the Professional Engineer,
fire alarm technician, and the installing company.
SD-10 Operation and Maintenance Data
Operating and Maintenance Instructions[; G][; G, [_____]]