3.2
SYSTEM STARTUP
until the following items have been completed:
a.
up in accordance with manufacturer's instructions.
b.
A visual inspection of the intrusion detection system has been
conducted to ensure that defective equipment items have not been
installed and that there are no loose connections.
c.
System wiring has been tested and verified as correctly connected
as indicated.
d.
All system grounding and transient protection systems have been
verified as properly installed and connected as indicated.
e.
have been verified as the correct voltage, phasing, and frequency
as indicated.
f.
Satisfaction of the above requirements shall not relieve the
Contractor of responsibility for incorrect installation, defective
equipment items, or collateral damage as a result of Contractor
work/equipment.
3.3
SITE TESTING
3.3.1
General
supplies necessary to perform the site testing. The Government will
witness all testing. Written permission shall be obtained from the
Government before proceeding with the next phase of testing. Original
copies of all data produced during performance verification and endurance
testing shall be turned over to the Government at the conclusion of each
phase of testing prior to Government approval of the test.
3.3.2
Contractor's Field Testing
The Contractor shall calibrate and test all equipment, verify data
transmission system (DTS) operation, place the integrated system in
service, and test the integrated system. Ground rods installed by the
Contractor shall be tested as specified in IEEE Std 142. The Contractor
shall deliver a report describing results of functional tests, diagnostics,
and calibrations including written certification to the Government that the
installed complete system has been calibrated, tested, and is ready to
begin performance verification testing. The report shall also include a
copy of the approved performance verification test procedure.
3.3.3
Performance Verification Test
The Contractor shall demonstrate that the completed system complies with
the specified requirements. Using approved test procedures, all physical
and functional requirements of the project shall be demonstrated and shown.
The performance verification test, as specified, shall not be started
until receipt by the Contractor of written permission from the Government,
based on the Contractor's written request. This shall include
SECTION 13721A
Page 34