involved. Specify minimum requirements for
abatement of asbestos outdoors where construction of
a containment is not practical. The designer will
provide the best suited, specific requirements
necessary for the particular project to prohibit or
reduce asbestos exposure to other Contractor
employees, customer resources and the general public.
**************************************************************************
Asbestos abatement work tasks shall be performed [as shown on the detailed
plans and drawings,] as summarized in Table 1. The Contractor shall use
the engineering controls and work practices required in 29 CFR 1926.1101(g)
in all operations regardless of the levels of exposure. Personnel shall
not permit eating, smoking, drinking, chewing or applying cosmetics in the
regulated area. Personnel of other trades, shall not be exposed at any
time to airborne concentrations of asbestos unless all the administrative
and personal protective provisions of the Contractor's APP are complied
with. Power to the regulated area shall be locked-out and tagged in
accordance with 29 CFR 1910.147, and temporary electrical service with
ground fault circuit interrupters shall be provided as needed. Temporary
electrical service shall be disconnected when necessary for wet removal.
The Contractor shall stop abatement work in the regulated area immediately
when the airborne total fiber concentration: (1) equals or exceeds 0.01
f/cc, or the pre-abatement concentration, whichever is greater, outside the
regulated area; or (2) equals or exceeds 1.0 f/cc inside the regulated
area. The Contractor shall correct the condition to the satisfaction of
the CO, including visual inspection and air sampling. Work shall resume
only upon notification by the CO. Corrective actions shall be documented.
3.2
PROTECTION OF ADJACENT WORK OR AREAS TO REMAIN
Asbestos abatement shall be performed without damage to or contamination of
adjacent work or area. Where such work or area is damaged or contaminated,
it shall be restored to its original condition or decontaminated by the
Contractor at no expense to the Government. When spills occur, work shall
stop in all effected areas immediately and the spill shall be cleaned.
When satisfactory visual inspection and air sampling analysis results are
obtained and have been evaluated by the Contractor's Designated IH and the
CO, work shall proceed.
3.3
OBJECTS
**************************************************************************
NOTE: When the Government will remove objects,
furniture and equipment, there are no Contractor
requirements; therefore, select the first bracketed
sentence. If the Contractor is to remove or protect
objects and furnishings, complete DETAIL SHEET 27,
and include appropriate bracketed sentences and
paragraphs. Remove subparagraphs that do not apply.
**************************************************************************
3.3.1
Removal of Mobile Objects
[The Government will remove Furniture, [_____] and equipment from the area
of work before work begins.] [DETAIL SHEET 27 contains a summary of
Contractor's required handling, cleaning and storage and reinstallation of
furniture and equipment located in each abatement area. Furnishings