3.2.5
Installation of Gutters and Downspouts
Gutters and downspouts shall be rigidly attached to the building. Spacing
of cleats for gutters shall be 400 mm 16 inches maximum. Spacing of
brackets and spacers for gutters shall be 1 m 36 inches maximum. Supports
for downspouts shall be spaced according to manufacturer's recommendations.
3.2.6
Louvers and Ventilators
Louvers and ventilators shall be rigidly attached to the supporting
construction to assure a weather tight installation.
3.2.7
Doors and Windows
Doors and windows, including frames and hardware, shall be securely
anchored to the supporting construction, shall be installed plumb and true,
and shall be adjusted as necessary to provide proper operation. Joints at
doors and windows shall be sealed according to manufacturer's
recommendations to provide weathertight construction.
3.2.8
Minimum Fastener Spacing
Space fasteners according to manufacturer's instructions, but not to exceed:
a.
200 mm 8 inches o.c. at end laps of covering,
b.
300 mm 12 inches o.c. at connection of covering to intermediate
supports,
c.
300 mm 12 inches o.c. side laps of roof coverings, 450 mm 18 inches
o.c. at side laps of wall.
3.2.9
Installation of Insulation
**************************************************************************
NOTE: If factory insulated panels are used for
roofing and siding, delete this paragraph in its
entirety.
**************************************************************************
**************************************************************************
NOTE: These paragraphs are limited to mineral fiber
insulations of a 150 mm 6 inch thickness or less.
If thicker insulation is required, consult metal
building manufacturer for recommendations for
installation.
**************************************************************************
**************************************************************************
NOTE: Choose the bracketed option only when
insulation must be stapled from the interior of the
building and concealment of the joints is desired.
**************************************************************************
3.2.9.1
Roof Insulation
Install over purlins before roof coverings are applied. Hold insulation
rigid until secured in place. Insulation facing shall be exposed on the
interior side of the building. Fold and staple facing tabs of insulation on
SECTION 13120
Page 41