Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Detail Drawings[; G][; G, [_____]]
list of equipment and material including manufacturer's
descriptive and technical literature, catalog cuts, results of
maximum recommended anode current output density and the rate of
gaseous production, if any, at that current density. Detail
any other details required to demonstrate that the system has been
coordinated and will function properly as a unit.
Contractor's Modifications[; G][; G, [_____]]
in location, scope or performance indicating any variations from,
additions to, or clarifications of contract drawings. The
drawings shall show proposed changes in anode arrangement, anode
size and number, anode materials and layout details, conduit size,
electrically isolating each pipe, and any other pertinent
information to the proper installation and performance of the
system.
SD-03 Product Data
Within [30] [45] [_____] days after receipt of notice to
proceed, an itemized list of equipment and materials including
item number, quantity, and manufacturer of each item. The list
shall be accompanied by a description of procedures for each type
of testing and adjustment, including testing of coating for
thickness and holidays. Installation of materials and equipment
shall not commence until this submittal is approved.
Spare Parts
Spare parts data for each different item of material and
equipment specified.
SD-06 Test Reports
Tests and Measurements
Test reports in booklet form tabulating field tests and
measurements performed, upon completion and testing of the
installed system and including close interval potential survey,
SECTION 13112A