projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Comminutor[; G][; G, [_____]]
Drawings indicating clearances required for maintenance and
equipment layout and anchorage, and any other details required to
demonstrate that the system has been coordinated and will properly
function as a unit.
SD-03 Product Data
Spare Parts
Spare parts data for each different item of materials and
equipment specified, after approval of the drawings and not later
than [_____] months prior to the date of beneficial occupancy .
The data shall include a complete list of parts and supplies with
current unit prices and source of supply.
Materials and Equipment
A complete list of equipment and materials, including
manufacturer's descriptive and technical literature, catalog cuts,
Framed Instructions
Proposed diagrams, instructions, and other sheets, prior to
SD-06 Test Reports
Field Tests
Test reports in booklet form showing all field tests performed
on the installed system to adjust each component and all field
tests performed to prove compliance with the specified performance
criteria. Each test report shall indicate the final position of
controls.
SD-10 Operation and Maintenance Data
SECTION 11331
Page 5