coating system is ideal for repairing and coating of
galvanized surfaces. Repair galvanizing with the
zinc-rich primer, and apply general coats of
intermediate and topcoat to all surfaces.
**************************************************************************
**************************************************************************
NOTE: This specification should be edited by
personnel familiar with protective coatings and
coating specifications. Completion of SSPC Course
"C-1 Fundamentals of Protective Coatings For
Industrial Structures," or equivalent, is considered
a minimal qualification, along with appropriate
specification writing experience.
**************************************************************************
**************************************************************************
NOTE: This guide specification complies with the
intent of Air Force ETL 86-4, as revised on 28
April, 1999 to eliminate the "second primer coat."
**************************************************************************
**************************************************************************
NOTE: The metric standard for measuring coating
thickness is microns (25.4 microns=1 mil - use
nominal 25 microns=1 mil).
**************************************************************************
**************************************************************************
NOTE: This specification is for an industry
standard, 3 Coat, thin film, coating system that is
compliant with EPA VOC regulations as of June 2000:
- Epoxy coats 350 g/l 2.8#/gal max. VOC
- Polyurethane Topcoat 350 g/l 2.8#/gal max. VOC
The designer shall review state and local,
regulations and determine whether the coating in
this Section complies with restrictions on volatile
organic components (VOC) and other chemical
constituents.
**************************************************************************
**************************************************************************
NOTE: Previous versions of this specification have
included a requirement for surfaces to be abrasive
blasted to SSPC SP 7, inspected, and repaired, prior
to coating. That requirement has been removed from
this specification, and if required for a repair
project, it should be included in the structural
repair Section of the project specification. Tailor
the paragraph to the needs of cleaning that will be
required in preparation for repairs, and note that
accomplished in such a manner that it does not
conflict with any surface condition requirements in
this Section, such as creating excessive surface
profile that may require excessive primer thickness.
For repair projects, specify appropriate portions
SECTION 09971