b.
Strippability: On cementitious substrate surfaces, after asphalt
used in the foaming test application has cooled to ambient
temperatures, test coating for adherence.
Should a portion of
the sample be readily stripped clean from the surface, do not
consider the surface to be dry and do not start application.
Should rain occur during application, stop work and do not resume
until surface has been tested by the method above and found dry.
]3.5.2
Construction Monitoring
During progress of the roof work, Contractor shall make visual inspections
as necessary to ensure compliance with specified parameters. Additionally,
verify the following:
Materials comply with the specified requirements.
a. Materials are not installed in adverse weather conditions.
All materials are properly stored, handled and protected from
moisture or other damages.
b.
Equipment is in working order.
Metering devices are accurate.
c. Substrates are in acceptable condition, in compliance with
specification, prior to application of subsequent materials.
Nailers and blocking are provided where and as needed.
Insulation substrate is smooth, properly secured to its substrate,
and without excessive gaps prior to membrane application.
The proper number, type, and spacing of fasteners are installed.
Membrane heating, hot mopping, or adhesive application is provided
uniformly and as necessary to ensure full adhesion of roll
materials. Asphalt is heated and applied within the specified
temperature range.
The proper number and types of plies are installed, with the
specified overlaps.
Applied membrane surface is inspected, cleaned, dry, and repaired
as necessary prior to cap sheet installation.
Lap areas of all plies are full sealed.
Membrane is fully adhered without ridges, wrinkles, kinks,
fishmouths, or other voids or delaminations.
Installer adheres to specified and detailed application parameters.
Associated flashings and sheet metal are installed in a timely
manner in accord with the specified requirements.
Temporary protection measures are in place at the end of each work
shift.