applied in accordance with Section 09900 PAINTS AND COATINGS.
1.3
SUBMITTALS
**************************************************************************
NOTE: Submittals must be limited to those necessary
for adequate quality control. The importance of an
item in the project should be one of the primary
factors in determining if a submittal for the item
should be required.
A "G" following a submittal item indicates that the
submittal requires Government approval. Some
submittals are already marked with a "G". Only
delete an existing "G" if the submittal item is not
complex and can be reviewed through the Contractor's
submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] All items designated with a "G", including product
literature, calculations, component data, certificates, diagrams, drawings,
and samples shall be submitted concurrently in one complete system
submittal. Omission of any required submittal item from the package shall
be sufficient cause for disapproval of the entire submittal. Unless
otherwise indicated in the submittal review commentary, disapproval of any
item within the package shall require a re-submittal of the entire system
package, in which all deficiencies shall be corrected. The following shall
be submitted in accordance with Section 01330 SUBMITTAL PROCEDURES:
.
SD-02 Shop Drawings
Shop Drawings
Installation