CONCRETE REHABILITATION
09/99
**************************************************************************
NOTE: This guide specification covers the
requirements for repair of portland cement concrete
using epoxy resin grouts, mortars and concretes.
Comments and suggestions on this guide specification
are welcome and should be directed to the technical
proponent of the specification. A listing of
technical proponents, including their organization
designation and telephone number, is on the Internet.
Recommended changes to a UFGS should be submitted as
a Criteria Change Request (CCR).
Use of electronic communication is encouraged.
Brackets are used in the text to indicate designer
choices or locations where text must be supplied by
the designer.
**************************************************************************
**************************************************************************
NOTE: Select appropriate title for type of repair
work in contract. For repairs involving bonding new
Portland cement concrete to old Portland cement
concrete using epoxy resin binder use Section 02752
PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES or Section 03300N CAST-IN-PLACE CONCRETE
depending on project requirements.
**************************************************************************
**************************************************************************
NOTE: The following information should be shown on
1. Location and extent of spalled, cracked or
damaged concrete to be repaired with epoxy;
2. Location and extent of cracked concrete or saw
kerfs to be filled with epoxy mortar;
3.
Location of dowels to be installed and cracks to
SECTION 03930
Page 3