submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Erection[; G][; G, [_____]]
ACI 318M/318RM ACI 318/318R, including installation details.
each different precast unit, location of units in the work,
elevations, fabrication details, welding details, reinforcement,
connections, dimensions, interface with adjacent members, blocking
points for units stored at the precast concrete plant or at the
jobsite, lifting points and special handling instructions in
sufficient detail to cover manufacture, handling, and erection.
SD-03 Product Data
Calculations[; G][; G, [_____]]
Design calculations, prior to the manufacture of any precast
architectural concrete units for the project.
Mix Design[; G][; G, [_____]]
A statement on the mix design formula, as specified.
Manufacturer's Qualifications
A statement giving the qualifications of the precast concrete
manufacturer and of the installers, prior to commencing operations.
SECTION 03413A
Page 5