arrangement, and size of the pipe and inserts, sequence of
pumping, method of withdrawal of injection pipe, and the rate of
grout injection shall be included in the submittal. Methods for
venting of air from under embedded projections shall be submitted.
Vibrators
The Contractor shall submit data which include the size,
frequency, and amplitude of the external vibrators for review.
Testing and Quality Verification for Contractor Quality Control
technicians and the concrete inspectors meet the specified
requirements.
Curing and Protection[; G][; G, [_____]]
The curing medium and methods to be used shall be submitted for
review and approval.
Cold-Weather Placing[; G][; G, [_____]]
If preplaced-aggregate concrete is to be placed under
cold-weather conditions, the proposed materials, methods, and
protection meeting the requirements of paragraph COLD-WEATHER
PLACING OF PREPLACED-AGGREGATE CONCRETE shall be submitted for
approval.
Hot-Weather Placing[; G][; G, [_____]]
Finishing[; G][; G, [_____]]
If preplaced-aggregate concrete is to be placed under
hot-weather conditions, the proposed materials and methods,
meeting the requirements of paragraph HOT-WEATHER PLACING OF
PREPLACED-AGGREGATE CONCRETE and paragraph FINISHING, shall be
submitted for review and approval by the Contracting Officer.
SD-04 Samples
Aggregates[; G][; G, [_____]]
Cementitious Materials, Admixtures, and Curing Compound[; G][; G,
[_____]]
Samples of materials for Government testing and approval shall
be submitted as required in paragraph PRECONSTRUCTION SAMPLING AND
TESTING.
SD-06 Test Reports
Quality of Aggregates[; G][; G, [_____]]
Aggregate quality test results shall be submitted at least 30
days prior to start of preplaced-aggregate concrete placement, in
accordance with paragraph QUALITY OF AGGREGATES.
Testing and Quality Verification for Contractor Quality Control
Contractor quality control test results and inspection reports
SECTION 03372