3.1.1.2
Canopy Pruning
Canopy pruning shall conform to ANSI A300.
3.1.2
Plant Material Preparation
Plant material designated for transplanting shall be watered thoroughly
several days before root pruning, digging or moving. Broken or interfering
growth shall be pruned. Large canopy and specimen plant material shall be
[wire balled and burlapped] [boxed][bare rooted][spaded]. Mark north side
of plants prior to excavation. Relocate in new location with north facing
same direction.
3.1.3
Palms
In preparation for relocation, remove all dead and green fronds below a
horizontal position with clean, sterilized equipment and tools. All fronds
above horizontal shall be lifted and tied together in two locations around
the crown in an upright position with a light weight cotton rope. Removal
of fronds and tying shall be completed prior to digging the root ball.
Palms trimmed or pruned shall retain a minimum 150 mm6 inches of foliage at
the crown as a means of determining plant health.
3.2
SITE PREPARATION
3.2.1
Finish Grade and Topsoil
**************************************************************************
NOTE: Coordinate the placement of topsoil with
Section 02300, "Earthwork". When stockpiled topsoil
is limited, define the areas that will use this
soil.
**************************************************************************
The Contractor shall verify that finish grades are as indicated on
drawings, and that the placing of topsoil, the smooth grading, and the
compaction requirements have been completed in accordance with Section [
02300 EARTHWORK][02315N EXCAVATION AND FILL], prior to the commencement of
the transplanting operation.
3.2.2
Layout
Relocate plant material as shown on drawings. Plant material locations may
be adjusted to meet field conditions, only with Contracting Officer
approval.
3.3
SITE EXCAVATION
3.3.1
Obstructions Above or Below Ground
When obstructions above or below ground affect the work, shop drawings
showing proposed adjustments to plant material location, and planting
method shall be submitted for Government approval.
3.3.2
Turf Removal and Replacement
Where the installation operation occurs in an existing lawn area, the turf
shall be removed from the excavation area to a depth that will ensure the
SECTION 02915
Page 15