vehicle barrier. The test shall include raising and lowering the barrier,
both electrically and manually, through its complete range of operation.
Each vehicle barrier shall then be continuously cycled for not less than 30
minutes to test for heat build-up in the hydraulic system. The Contracting
Officer shall be notified at least 7 days prior to the beginning of the
field test. The Contractor shall furnish all equipment and make all
necessary corrections and adjustments prior to tests witnessed by the
Contracting Officer. Any conditions that interfere with the proper
operation of the barrier disclosed by the test shall be corrected at no
additional cost to the Government. Adjustments and repairs shall be done
by the Contractor under the direction of the Contracting Officer. After
adjustments are made to assure correct functioning of components,
applicable tests shall be completed.
3.6
FIELD TRAINING
**************************************************************************
NOTE: For electrical/hydraulic option, select 8
hour requirement. For the manual option, select the
1-hour requirement.
**************************************************************************
A field training course shall be provided for designated operating staff
members. Training shall be provided for a total period of not less than [8
hours] [1 hour] of normal working time and shall start after the system is
functionally complete but prior to final acceptance tests. Field training
shall cover all of the items contained in the operating and maintenance
instructions.
-- End of Section --