the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
**************************************************************************
NOTE: Omit this requirement when contract drawings
are so detailed that additional drawings would serve
no useful purpose or when there is no requirement
for special items such as sliding gates or
turnstiles.
**************************************************************************
Gates
Turnstiles
Post spacing
Location of gate, corner, end, and pull posts
SD-03 Product Data
Chain-link fencing components
Accessories
SD-06 Test Reports
**************************************************************************
NOTE: Require test reports where closer product
control is essential or where difficulty might be
encountered determining quality of supplied
materials.
**************************************************************************
Weight in grams for zinc coatingWeight in grams ounces for zinc
coating
SECTION 02821N