District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for [Contractor Quality Control
approval.] [information only. When used, a designation following the "G"
designation identifies the office that will review the submittal for the
Government.] The following shall be submitted in accordance with Section
01330 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Fabricated Additions[; G][; G, [_____]]
prior to commencing work or ordering materials.
Pile Driving
A complete and accurate record of each driven pile, within 3
days of completion of driving. The record shall indicate the pile
location (as driven), size, driven length, embedded length, final
elevations of tip and top, pile weight, number of splices and
locations, blows required for each 305 mm foot of penetration
throughout the entire length of the pile and for the final 150 mm
6 inches of penetration, and the total driving time. The record
shall also include the type and size of the hammer used, the rate
of operation, and the type and dimensions of driving helmet and
cushion block used. Any unusual conditions encountered during
pile installation shall be recorded and immediately reported to
the Contracting Officer.
SD-03 Product Data
Equipment
Description of pile driving equipment to be employed in the
work, prior to commencement of pile installations; including
details of the pile hammer, power plant, leads, cushion material,
and helmet.
SD-06 Test Reports
Field Tests and Inspections
A complete report on the load test, including, but not limited
to, a description of the pile driving equipment, driving records
for both test piles and reaction piles, complete test data,
analysis of test data, and recommended allowable design loads
based on the load test results, within [7] [_____] days of
completion of load test. The report shall be prepared by or under
SECTION 02456A
Page 7