The publications listed below form a part of this specification to the
extent referenced. The publications are referred to within the text by the
basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D 3740
(2004) Minimum Requirements for Agencies
Engaged in the Testing and/or Inspection
of Soil and Rock as Used in Engineering
Design and Construction
ASTM E 329
(2003) Agencies Engaged in the Testing
and/or Inspection of Materials Used in
Construction
U.S. ARMY CORPS OF ENGINEERS (USACE)
ER 1110-1-12
(1993) Quality Management
1.2
PAYMENT
Separate payment will not be made for providing and maintaining an
effective Quality Control program, and all costs associated therewith shall
be included in the applicable unit prices or lump-sum prices contained in
the Bidding Schedule.
PART 2
PRODUCTS (Not Applicable)
PART 3
EXECUTION
3.1
GENERAL REQUIREMENTS
**************************************************************************
NOTE: Selection of construction or design-build
construction text required.
**************************************************************************
The Contractor is responsible for quality control and shall establish and
Contract Clause titled "Inspection of Construction." The quality control
system shall consist of plans, procedures, and organization necessary to
produce an end product which complies with the contract requirements. The
system shall cover all constructiondesign and construction operations, both
onsite and offsite, and shall be keyed to the proposed construction
sequence. The site project superintendent will be held responsible for the
quality of work on the job and is subject to removal by the Contracting
Officer for non-compliance with the quality requirements specified in the
contract. The site project superintendent in this context shall be the
highest level manager responsible for the overall construction activities
at the site, including quality and production. The site project
superintendent shall maintain a physical presence at the site at all times,
except as otherwise acceptable to the Contracting Officer, and shall be
responsible for all construction and construction related activities at the
site.
SECTION 01451A