will be cause for rejection of the submitted schedule.
The schedule shall
identify as a minimum:
a.
[Design and ]Construction time for all major systems and
components;
b.
Each activity shall be assigned its appropriate Responsibility
Code;
c.
Each activity shall be assigned its appropriate Phase Code;
d.
Major submittals and submittal processing time; and
e.
Major equipment lead time].
**************************************************************************
NOTE: When WebCM is a requirement on this project,
delete the first bracketed phrase and retain the
language in the second set of brackets.
**************************************************************************
1.4.1
CPM Submittals and Procedures
Submit all network analysis and updates in hard copy and [on electronic
media that is acceptable to the Contracting Officer][the backed-up native
files (.prx or .stx) for the schedule submittal will be posted to the
NAVFAC WebCM internet site, as directed by the Contracting Officer. The
project schedule will also be posted in the format specified as an Adobe
PDF file with no relationship lines displayed in the graphic]. The network
analysis system shall be kept current, with changes made to reflect the
actual progress and status of the construction.
]1.5
UPDATED SCHEDULES
Update the construction schedule and equipment delivery schedule at monthly
intervals or when the schedule has been revised. Reflect any changes
occurring since the last update. Submit copies of the purchase orders and
confirmation of the delivery dates as directed.
PART 2
PRODUCTS
Not used.
PART 3
EXECUTION
Not used.
-- End of Section --