failure, and time and date of return to service. During the
30-day acceptance test, any operational failures due to
malfunction of the control panels, wiring, or Control Room
Equipment shall require that the 30 day test begin again when
repairs are completed. Any failures between field-sensing
equipment and the control panels shall be corrected, and the
testing shall continue from the day of failure. During the last
seven (7) calendar days of testing, no failures of any kind will
be accepted or the last seven (7) days shall be repeated. If the
season of the year prevents complete testing of any individual
upon the successful demonstration of the specific component at the
appropriate season.
e.
Final Acceptance: The control system will not be considered
accepted by the Government until all tests are successfully
completed. Beneficial use of the system by the Government will
not be considered as acceptance. The Government will deem the
control system to be fully accepted when:
1. Structured, unstructured and availability tests have been
successfully completed, and all incidents and variances have been
resolved to the Government's satisfaction.
2. Documentation and training requirements have been completed
and are satisfactory to the Government.
3. Maintenance and related contracts and releases of
subcontractors have been duly executed and submitted to the
Government.
4. Identified defects have been corrected to the Government's
satisfaction.
3.6.6.7
Boiler Room Panels and Instruments
After inspections of installation and calibration of instruments, and after
boiler test, Contractor shall provide a certificate of compliance to
fuel. If units fail to operate satisfactorily or fail to achieve specified
performance, Contractor shall make adjustments, modifications, repairs, or
replacements as necessary at no additional cost until specified performance
has been achieved and certified by Contracting Officer.
3.6.6.8
Temporary Piping for Testing
Necessary temporary piping, of not less than 100 mm 4 inches in diameter,
shall be furnished and a muffler shall be provided to exhaust excess steam
to atmosphere in event boiler load is insufficient to meet capacity
specified. Control valve for exhausting excess steam to atmosphere shall
be provided in a convenient location inside the boiler room. Instruments
required for conducting boiler tests shall be as described in ASME PTC 4
and ASME PTC 19.11. Temporary piping, valves, pipe hangers, mufflers and
test equipment shall be provided by Contractor at no additional cost.
Muffler shall have level of noise of exhaust steam within requirements as
set forth by Occupational Safety and Health Act.