h.
An analysis by an independent testing laboratory of fuel being
burned during test shall be submitted to the Contracting Officer.
Analysis shall include pertinent data tabulated in ASME PTC 4,
abbreviated efficiency test.
i.
Contracting Officer will observe and approve tests.
3.6.6.6
Control System Operational Testing
**************************************************************************
adding project specific equipment and sequences of
operation, alarms and other critical interface
points between contracts (such as mechanical and
Consider integrating these tests into a larger
**************************************************************************
a.
Full operational test of boiler plant control system shall be
conducted to demonstrate compliance with sequences of operation,
safety interlocks and control functions of the specification.
b.
Field Installation Test: Following the installation of the
control system, all hardware shall be aligned and adjusted, and
all test readings recorded in accordance with the manufacturer and
installer recommended tests and maintenance procedures.
Manufacturer and installer shall include in the associated test
report a list of all hardware or components replaced or changed
installation test. All hardware shall be demonstrated to be
operational by running off-line diagnostics. Field installation
test shall include electrical continuity, complete exercising of
each Input and Output point, and simulation of each control loop.
The field installation test shall be considered complete only
after all variances generated during installation are resolved and
tested.
c.
Startup Test and Punchout: Prior to on-line operation, conduct a
surveillance and control. Demonstration of controls shall include
simulation of analog inputs and observation of the action of
system final control elements. Generate a hardcopy printout and
perform punchout of all Input and Output points. Submit startup
test hardcopy printout to Contracting Officer two (2) weeks prior
be conducted in accordance with the control system sequences of
operation. Conduct startup test and punchout in the presence of
the Contracting Officer. The Contracting Officer shall be
notified no later than ten (10) days prior to scheduled startup
testing.
d.
Operational Acceptance Test: After all previous testing has been
successfully completed, operate control system for thirty (30)
days to the complete satisfaction of the Contracting Officer.
Submit to Contracting Officer a bound log reporting all control
system failures that occur red during operational acceptance test.
Log shall show the point name and number, time and date of