3.2.1.3
Insulation Resistance
Insulation resistance wire to wire of wireline pair of at least 16,093
megohm-km 10,000 megohm-miles measured at 22 degrees C 72 degrees F.
3.2.1.4
Loop Resistance
3.2.2
Contractor's Field Test
**************************************************************************
NOTE: Designer must insert the title of the
appropriate specification.
**************************************************************************
The Contractor shall verify complete operation of the DTS during
Contractor's Field Testing as specified in Section [_____]. Field test
shall include a bit error rate test. The Contractor shall perform the test
by sending a minimum of 100,000 bits of data on each communication link and
measuring errors. The bit error rate shall be not greater than 1 out of
100,000 for each link. The Contractor shall prepare a report containing
results of the field test.
3.2.3
Verification Test and Endurance
The wire line data transmission system shall be tested during the
Performance Verification Test and Endurance Test as specified in Section
[_____].
-- End of Section --
SECTION 16792A
Page 19