3.7.2
Manufacturer's Representative
The engine generator-set manufacturer shall furnish a qualified
representative to supervise the installation of the engine generator-set,
assist in the performance of the onsite tests, and instruct personnel as to
the operational and maintenance features of the equipment.
3.8
INSTRUCTIONS
**************************************************************************
NOTE: The designer should check with the customer
to determine if framed instructions can be placed in
the project area (requires wall space), and where
they are to be placed. Select the 216 x 279 mm (8
1/2 x 11 inches) notebook option where instructions
will have to be placed in the genset enclosure or a
switchgear cubicle (or other suitable enclosure).
**************************************************************************
[Two sets of instructions shall be typed and framed under weatherproof
laminated plastic, and posted side-by-side where directed before
acceptance. First set of instructions shall include a one-line diagram,
wiring and control diagrams and a complete layout of the system. Second
describing manufacturer's pre-start checklist and precautions; start
procedures for test-mode, manual-start mode, and automatic-start mode (as
applicable); running checks, procedures, and precautions; and shutdown
procedures, checks, and precautions. Instructions shall include procedures
for interrelated equipment (such as heat recovery systems, co-generation,
load-shedding, and automatic transfer switches).] [Two sets of
instructions shall be typed in 216 x 279 mm 8 1/2 x 11 inches format,
laminated in weatherproof plastic, and placed in three-ring vinyl binders.
The binders shall be placed as directed by the Contracting Officer. The
instructions shall be in place prior to acceptance of the engine generator
set installation. First set of instructions shall include a one-line
diagram, wiring and control diagrams and a complete layout of the system.
Second set of instructions shall include the condensed operating
instructions describing manufacturer's pre-start checklist and precautions;
startup procedures for test-mode, manual-start mode, and automatic-start
mode (as applicable); running checks, procedures, and precautions; and
shutdown procedures, checks, and precautions. Instructions shall include
procedures for interrelated equipment (such as heat recovery systems,
co-generation, load-shedding, and automatic transfer switches).]
3.9
ACCEPTANCE
Final acceptance of the engine-generator set will not be given until the
Contractor has successfully completed all tests and after all defects in
installation material or operation have been corrected.
-- End of Section --