particles, etc. Any corrective action shall be verified for
effectiveness by running the engine for 8 hours at Service Load,
then re-examining the oil and filter.
e.
Remove the fuel filter and examine the filter for trash, abrasive
foreign particles, etc.
f.
Visually inspect and check engine and generator mounting bolts for
tightness and visible damage.
g.
3.6
POSTED DATA AND INSTRUCTIONS
**************************************************************************
NOTE: The designer should check with the customer
to determine if framed instructions can be placed in
the project area (requires wall space), and where
they are to be placed. Select the 8 1/2" X 11"
notebook option where instructions will have to be
placed in the genset enclosure or a switchgear
cubicle (or other suitable enclosure).
**************************************************************************
Posted Data and Instructions shall be posted prior to field acceptance
testing of the engine generator set. [Two sets of instructions/data shall
be typed and framed under weatherproof laminated plastic, and posted
side-by-side where directed. First set shall include a one-line diagram,
wiring and control diagrams and a complete layout of the system. Second
manufacturer's pre-start checklist and precautions; startup procedures for
test-mode, manual-start mode, and automatic-start mode (as applicable);
running checks, procedures, and precautions; and shutdown procedures,
checks, and precautions. Instructions shall include procedures for
interrelated equipment (such as heat recovery systems, co-generation,
load-shedding, and automatic transfer switches).] [Two sets of
instructions/data shall be typed in 8 1/2" x 11" format, laminated in
weatherproof plastic, and placed in three-ring vinyl binders. The binders
shall be placed as directed by the Contracting Officer. The instructions
shall be in place prior to acceptance of the engine generator set
installation. First set shall include a one-line diagram, wiring and
control diagrams and a complete layout of the system. Second set shall
pre-start checklist and precautions; startup procedures for test-mode,
manual-start mode, and automatic-start mode (as applicable); running
checks, procedures, and precautions; and shutdown procedures, checks, and
precautions. Instructions shall include procedures for interrelated
equipment (such as heat recovery systems, co-generation, load-shedding, and
automatic transfer switches).]
3.7
ONSITE TRAINING
**************************************************************************
NOTE: Delete video taping if not required.
**************************************************************************
The Contractor shall conduct training course for operating staff as
designated by the Contracting Officer. The training period shall consist
of a total [_____] hours of normal working time and shall start after the
SECTION 16263A