period is completed shall result in the test period being started
again and run for the required duration. For the duration of the
test period, compile an operational log of each item of equipment.
Log required entries every 2 hours. Use the test report forms
for logging the operational variables.
d.
Notice of Tests: Conduct the manufacturer's recommended tests and
reporting forms. Notify the Contracting Officer in writing at
least 15 calendar days prior to the testing. Within 30 calendar
days after acceptable completion of testing, submit each test
report for review and approval.
e.
Report Forms: Type data entries and writing on the test report
forms. Completed test report forms for each item of equipment
shall be reviewed, approved, and signed by the Contractor's test
director and the QC Manager. The manufacturer's field test
representative shall review, approve, and sign the report of the
manufacturer's recommended test. Signatures shall be accompanied
by the person's name typed.
f.
Deficiency Resolution: The test requirements acceptably met;
deficiencies identified during the tests shall be corrected in
compliance with the manufacturer's recommendations and corrections
retested to verify compliance.
3.7.5
Additional Field Testing
**************************************************************************
NOTE: In the following paragraph, use Section
15950, "HVAC Testing/Adjusting/Balancing" for
systems larger than 52,700 W 180,000 Btuh.
**************************************************************************
**************************************************************************
NOTE:
Use LANTNAVFACENGCOM Section 15949, "HVAC
Testing/Adjusting/Balancing For Small Systems" for
small systems" less than 52,700 W 180,000 Btuh and
larger than 28,100 W 96,000 Btuh.
**************************************************************************
[Requirements for testing, adjusting, and balancing (TAB) of ducts, piping,
and equipment are specified in Section 15950N HVAC
TESTING/ADJUSTING/BALANCING.]
**************************************************************************
NOTE: Use this paragraph for each building which
has less than 28.1 kW 96,000 Btuh of cooling, less
than 372 square meters 4000 square feet of floor
space, or less than 15 supply air outlets. Include
bracketed option for LANTNAVFACENGCOM projects.
**************************************************************************
[Balance air flows to that indicated in accordance with SMACNA HVAC Duct
Const Stds, as supplemented and modified by this section. Submit written
certificate to report the following:
a.
Water source heat pump unit nameplate data, and actual voltage and
ampere consumption.