Upon completion of evacuation, charging, startup, final leak testing, and
proper adjustment of controls, test the systems to demonstrate compliance
with performance and capacity requirements. Test systems for not less than
8 hours, record readings hourly. At the end of the test period, average
the readings, and the average shall be considered to be the system
performance. Record the following readings:
[_____]
[_____]
3.9
SCHEDULE
Some metric measurements in this section are based on mathematical
conversion of inch-pound measurements, and not on metric measurements
commonly agreed on by the manufacturers or other parties. The inch-pound
and metric measurements shown are as follows:
Products
Inch-Pound
Metric
a.
[_____
_____
_____]
-- End of Section --
SECTION 15730N
Page 29