except as otherwise specified.
3.1.1
Heaters shall be installed with clearance to combustibles complying with
minimum distances as determined by CSA Directory, UL Gas&Oil Dir and as
indicated on each heater approval and listing plate. Heaters shall be
independently supported from the building structure as indicated and shall
not rely on support from suspended ceiling systems.
3.1.2
Vents
Vent dampers, piping and structural penetrations shall be located as
indicated. Vent damper installation shall conform to ANSI Z21.66. Vent
pipes, where not connected to a masonry chimney conforming to NFPA 211,
shall extend through the roof or an outside wall and shall terminate, in
compliance with NFPA 54. Vents passing through waterproof membranes shall
be provided with the necessary flashings to obtain waterproof installations.
3.1.3
Gas Piping
Gas piping shall be connected as indicated and shall comply with the
applicable requirements at Section 15190A GAS PIPING SYSTEMS.
3.2
TESTING, ADJUSTING, AND BALANCING
Testing, adjusting, and balancing shall be as specified in Section 15990A
TESTING, ADJUSTING, AND BALANCING OF HVAC SYSTEMS.
3.3
Training
**************************************************************************
NOTE: Insert the number of hours to train personnel
for equipment operations. Consult equipment
manufacturer for recommended time.
**************************************************************************
The Contractor shall conduct a training course for the maintenance and
operating staff. The training period of [_____] hours normal working time
shall start after the system is functionally complete but before the final
acceptance tests. The training shall include all of the items contained in
the approved operation and maintenance instructions as well as
demonstrations of routine maintenance operations. The Contracting Officer
shall be given at least two weeks advance notice of such training.
-- End of Section --
SECTION 15565A
Page 11