3.3.4
Balancing
Systems shall be completely balanced by a qualified engineer. A complete
balancing procedure shall be submitted for approval. All required piping,
valves, and connections required to balance the systems shall be provided.
Balancing of air systems shall be as specified in Section 15895 AIR SUPPLY,
DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEM.
3.3.5
Retesting
Any deficiencies revealed during testing shall be corrected and tests shall
be reconducted.
3.4
FIELD PAINTING
**************************************************************************
required by the using agency will be developed and
inserted in the "Color Code Schedule" in Section
09900 PAINTS AND COATINGS.
**************************************************************************
Painting required for surfaces not otherwise specified, and finish painting
of items only primed at the factory, are specified in Section 09900 PAINTS
AND COATINGS.
-- End of Section --
SECTION 15562A
Page 40