SD-07 Certificates
Welding procedure
Welder's Performance Qualification Record
List of welders and welder's symbols
Year 2000 (Y2K) Compliance Warranty; G
SD-08 Manufacturer's Instructions
Unit heaters
Convertors
Condensate return pumping units
Include manufacturer's recommendations for equipment foundations.
1.4
QUALITY ASSURANCE
1.4.1
Welding Procedure
Submit welding procedure specification for metals included in the work,
together with proof of the procedure's qualifications as outlined in ASME
B31.1.
1.4.2
Welder's Performance Qualification Record
Submit [to the Contracting Officer] the Welder's Performance Qualification
Record in conformance with ASME B31.1 for each welder, showing that the
welder was tested under the approved procedure specification submitted by
the Contractor. In addition, the Contractor shall submit list of welders
and welder's symbols, assigned number, or letter which shall be used to
identify the work of the welder which shall be affixed immediately upon
completion of the weld. Welders making defective welds after passing a
qualification test shall be required to take a requalification test.
Welders failing the requalification tests will not be permitted to work
under this contract.
1.4.3
Previous Qualifications
Welding procedures, welders, and welding operators previously qualified by
test may be accepted for this contract without requalification subject to
approval if the conditions specified in ASME B31.1 are met before a
procedure can be used.
1.5
WARRANTY
1.5.1
Year 2000 (Y2K) Compliance Warranty
For each product, component and system specified in this section as a
"computer controlled facility component", provide a statement of Y2K
compliance warranty for the specific equipment. The contractor warrants
that each hardware, software, and firmware product delivered under this
contract and listed below shall be able to accurately process date and time
data (including, but not limited to, calculating, comparing, and
SECTION 15183N
Page 12