1.0 inch of vertical adjustment (up or down) after runway installation.
Provide rods with self-aligning gimbal or ball-and-socket joints at each
end which allow at least 5.0 degrees of deflection from the vertical.
Provide not more than two rods per suspension point and in such cases
consider the unequal loads induced in the rods. Fluid-filled load
PART 3
EXECUTION
3.1
POST-ERECTION INSPECTION
After erection, the Contractor and the Contracting Officer shall jointly
inspect the crane bridge and hoist systems and components to verify
compliance with specifications and approved shop drawings and
manufacturer's data. The Contractor shall notify the Contracting Officer
[_____] days before the inspection.
The results of this inspection shall be documented by the Contractor and
the post-erection inspection report submitted to the Contracting Officer
for approval.
3.2
OPERATIONAL TEST
After erection and inspection, test the hoist, bridge, and trolley as
specified herein. All tests shall be witnessed by a technical
representative of the Contracting Officer.
The 125 percent rated load test shall be made with the bridge and trolley
located to obtain maximum loads on the runway and bridge girders. The
systems shall be tested in service to determine that each component of the
system operates as specified, is properly installed and adjusted, and is
free from defects in material, manufacture, installation, and workmanship.
The Contractor shall rectify all deficiencies disclosed by testing and
retest the system or component to prove the crane meets the specified
requirements.
The Contractor shall provide all personnel and equipment required to meet
the specified test requirements. This includes test loads, and rigging
gear, crane operating personnel, instruments, and all other necessary
apparatus.
3.2.1
Operational Test Report
Record crane test data on appropriate test record forms suitable for
retention for the life of the crane. Include in the test records:
a.
Test date
b.
Crane identification number
c.
Weather conditions (temperature, humidity, barometric pressure,
dew point, [prevailing wind direction and velocity,] and crane
orientation)
d.
Identification of each test performed
e.
Results of each test performed
f.
Data collected during testing
SECTION 14637N
Page 20