3.3
SCHEMATIC DIAGRAMS
drawings.
3.4
MANUFACTURER'S FIELD SERVICE REPRESENTATIVE
Contractor shall furnish a qualified experienced manufacturer's field
service representative to supervise the crane installation, assist in the
performance of the on site testing, and instruct personnel in the
operational and maintenance features of the equipment.
3.5
FIELD TRAINING
Contractor shall conduct a training course for the operating staff.
Training period shall consist of a total of [_____] hours of normal working
time and shall start after the system is functionally completed but prior
to final acceptance. Course instructions shall cover pertinent points
involved in operating, starting, stopping, and servicing the equipment,
Course instructions shall demonstrate all routine maintenance operations
such as lubrication, general inspection, and [_____]. Contracting Officer
shall be given at least 2 weeks advance notice of field training.
3.6
SPARE PARTS
One set of manufacturer's recommended spare parts shall be furnished and
delivered to the site. The spare parts shall be suitably packaged for
long-term protection and storage. The packaging shall be legibly labeled
to identify the spare parts. A list of the furnished spare parts shall be
included in the Maintenance manual.
3.7
ACCEPTANCE
**************************************************************************
NOTE: This paragraph should be used as written for
projects where the crane is the principal
construction element, or represents a very
significant portion of the Contract cost. However,
if the crane is part of a new facility or
renovation, the acceptance paragraph should be
deleted from this section. Warranty period and
operating and maintenance processes should not be
started before the actual beneficial occupancy of
the entire facility.
**************************************************************************
Final acceptance of crane system will not be given until Contractor has
successfully completed all testing operations, corrected all material and
equipment defects, made all proper operation adjustments, and removed paint
or overspray on wire rope, hook and electrical collector bars.
-- End of Section --