process]. Observe for any malfunctioning of the trolley assembly
and monorail system. [Operate all rail switches.]
3.3.7
Rated Load Speed Test
With the hoist loaded to rated capacity, raise and lower the load verifying
that the hoisting and lowering speeds are provided as specified. [With the
hoist loaded to rated capacity, operate trolley along the monorail beam
verifying that the trolley speed is provided as specified. Further, verify
that the trolley stops in each direction within a distance (in feet) equal
to 10 percent of rated capacity high speed (in feet per minute) when
initially travelling at high speed and carrying the rated capacity load.]
Record voltage, amperage, hoisting and lowering speeds, [trolley travel
-- End of Section --
SECTION 14622N
Page 16