3.5.3
Placing in Service
After final adjustment, the cathodic protection system shall be placed in
service and the condition of the system as left by the Contractor shall be
recorded and shall indicate transformer tap settings; voltage readings from
reference electrode to tank, readings both horizontal and vertical;
automatic control differential setting; ac supply voltage; adjusted dc
output voltage; and total protective current.
3.6
TRAINING
The Contractor shall conduct a training course for the operating staff as
designated by the Contracting Officer. The training period shall consist
of a total of [_____] hours of normal working time and shall start after
the system is functionally complete but prior to final acceptance tests.
The field instructions shall cover all of the items contained in the
operating and maintenance instructions, as well as demonstrations of
routine maintenance operations. The Contracting Officer shall be notified
at least 14 days prior to date of proposed starting of the training course.
-- End of Section --