2.9.9
Communications
Communications wiring shall be extended to, and installed in, the
electrified panels [and spine walls] as shown on the plans. Communications
outlets shall be installed at designated locations. Communications work
may be performed in conjunction with the installation of workstations or
may be separately executed at the Contractor's option; however, equipment,
materials, and installation shall conform to the requirements of [Section
16402 INTERIOR DISTRIBUTION SYSTEM] [Section 16710 BUILDING
TELECOMMUNICATIONS CABLING SYSTEM] [_____] and all interfaces must be
properly coordinated.
2.9.10
Special Systems
**************************************************************************
NOTE: Include this paragraph only in projects where
requirements for shielded facilities (TEMPEST,
Red/Black, EMP, etc.) and secure wiring have been
called out in project criteria. Specific
requirements for cable arrangement, separation of
Red/Black lines, etc., need to be verified for each
project. Provide metal raceway, channels, etc.
throughout. Separation distances required for
exposed cable or wiring in nonmetallic raceways are
much greater than for wiring installed in totally
enclosed metal raceway. Site specific details
and/or notes should be prepared for each project.
**************************************************************************
Designated raceway systems shall provide management for secure and
nonsecure power, computer and telecommunications cabling. Secure
distribution shall be separated from nonsecure distribution [in accordance
with details shown on the plans] [by running secure lines along top located
raceway and nonsecure along the bottom of the workstation panel [and spine
wall]].
PART 3
EXECUTION
3.1
INSTALLATION
The workstations shall be installed by certified installers in accordance
components shall be installed level, plumb, square, and with proper
alignment with adjoining furniture. The components shall be securely
interconnected and securely attached to the building where required. Three
sets of special tools and equipment necessary for the relocation of panels
and other components shall be furnished.
3.2
CLEANING
Upon completion of installation, all products shall be cleaned and polished
and the area shall be left in a clean and neat condition. Any defects in
material and installation shall be repaired, and damaged products that
cannot be satisfactorily repaired shall be replaced. The Contractor shall
-- End of Section --