complete mixing type.
1. Type of plant: (Extended aeration, Step
Aeration, or Complete Mixing).
2.
Design flow.
3.
5-day BOD loading.
4.
Suspended solids loading.
5. Whether a comminutor is needed for plants 1.09
L/s 25,000 GPD or less in size.
6.
Whether mechanical aerator should be allowed.
7. Whether plant should be concrete only, steel
only, or either concrete or steel at Contractor's
option.
8.
Whether piling is required for foundations.
9. Whether hypochlorinator or whether chlorinator
should be used for plants in 4.38 to 6.57 L/s
100,000 to 150,000 GPD range.
10. Whether raw sewage recirculation box
(recirculation to pumping station) is needed.
11. Whether plant is to be of aboveground or
belowground construction.
12.
Seismic loading (if necessary).
13.
Electric power characteristics for motors.
14. Whether automatic operation of air lift pumps
should be required.
15. Wind load and ice load for rotating sludge
collector.
16. Organic loading (5-day BOD) if other than that
given in the text.
17. Total suspended solids if other than given in
the text.
18. Size of hypochlorite mixing tank if larger
capacity than 113.4 L 30 gallons is needed.
19. Size of hypochlorite solution tank if larger
capacity than 208 L 55 gallons is needed.
20. Whether, for extended aeration type plant,
eventual conversion to step aeration type is
anticipated.
**************************************************************************
SECTION 11375N
Page 98