3.4
FIELD QUALITY CONTROL
3.4.1
Construction Monitoring
Contractor shall make visual inspections as necessary to ensure compliance
with specified requirements. Additionally, verify the following:
Materials comply with the specified requirements.
All materials are properly stored, handled and protected from
damage. Damaged materials are removed from the site.
a.
Framing and substrates are in acceptable condition, in compliance with
specification, prior to application of wall panels.
Panels are installed without buckles, ripples, or waves and in
uniform alignment and modulus.
Side laps are formed, sealed, fastened or seam locked as required.
The proper number, type, and spacing of attachment clips and
fasteners are installed.
Installer adheres to specified and detailed application parameters.
Associated flashings and sheet metal are installed in a timely
manner in accord with the specified requirements.
-- End of Section --