submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-04 Samples
[
Procedure qualification welds
SD-06 Test Reports
Ultrasonic tests
SD-07 Certificates
Rails
Welder's qualification
Welding procedure
[
[
Wet weather welding procedures]
Rail correction method
Rail preparation
SD-08 Manufacturer's Instructions
Thermite kit
SD-11 Closeout Submittals
Welded joint records
Submit as required by paragraph entitled "Joint Records."
1.3
QUALITY ASSURANCE
**************************************************************************
NOTE: Thermite welding processes and kits have been
developed by the following companies. There may be
other processes available. This Guide Specification
has been prepared with the processes of these
manufacturers in mind. If another manufacturer's
product is available in the vicinity of the activity
at which the work is to be performed, modify this
Guide Specification as necessary.
1. U.S. Orgotherm Inc., Lakehurst, NJ
08733,
Telephone: (201) 657-5781