Materials Disposition Records
Records which identify the incorporation of approved materials
into the work shall be submitted before completion of the contract.
Prestressing Operations Records
Complete records of the prestressing operations shall be
submitted before completion of the contract.
SD-06 Test Reports
Stressing Tendons and Accessories
Certified materials test reports shall be submitted for all
required materials tests, note the specific standards followed in
the performance of tests, show that materials comply with the
applicable specifications, be submitted for each material shipment
and be identified with specific lots prior to use of materials in
the work.
SD-07 Certificates
Certification of Prestressing Technicians
Certificates for prestressing technicians shall be submitted
prior to start of prestressing operations.
1.4
CERTIFICATION OF PRESTRESSING TECHNICIANS
Submitted certificates for prestressing technicians who will use the
proposed system in the work shall certify by name that these technicians
are thoroughly trained and skilled in the use of the system.
1.5
DELIVERY, STORAGE AND HANDLING OF MATERIALS
Materials shall be suitably wrapped, packaged or covered at the factory to
prevent being affected by dirt, water and rust. Materials shall be
protected against abrasion or damage during shipment and handling.
Materials stored at the site shall be placed above ground on elevated,
covered platforms.
PART 2
PRODUCTS
2.1
MATERIALS
Stressing tendons and accessories shall conform to the requirements of ACI
318M/318RM ACI 318/318R except as specified.
2.1.1
Stressing Tendons
Stressing tendons shall be clean and free of loose rust, scale and pitting.
Unbonded tendons shall be permanently protected from corrosion with an
approved applied coating.
2.1.1.1
Seven-Wire Stress-Relieved Strand and Strand Assemblies
Seven-wire stress-relieved strand and strand assemblies shall conform to
SECTION 03230
Page 6