Preliminary to providing a complete surface treatment, treat [three]
[_____] lengths of at least 30.5 m 100 feet each for the full width of the
distributor bar. Use the appropriate typical application rates specified
herein for one surface treatment trial. Make other surface treatment
trials using various amounts of materials as may be deemed necessary.
3.6
PROTECTION
Keep all traffic off surfaces freshly treated with bituminous material.
Provide sufficient warning signs and barricades so that traffic will not
travel over freshly treated surfaces. Protect the treated areas from
traffic for at least 24 hours after final application of bituminous
material and aggregate, or for such time as necessary to prevent picking
up. Immediately prior to opening to traffic, roll the entire treated area
with a self-propelled pneumatic-tired roller.
-- End of Section --