submittal is sufficiently important or complex in
context of the project.
For submittals requiring Government approval on Army
projects, a code of up to three characters within
the submittal tags may be used following the "G"
designation to indicate the approving authority.
Codes for Army projects using the Resident
Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
projects.
Submittal items not designated with a "G" are
considered as being for information only for Army
projects and for Contractor Quality Control approval
for Navy projects.
**************************************************************************
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are [for Contractor Quality Control
approval.][for information only. When used, a designation following the
"G" designation identifies the office that will review the submittal for
the Government.] The following shall be submitted in accordance with
Section 01330 SUBMITTAL PROCEDURES:
SD-03 Product Data
Piping
Fittings
Valves
Pipe coatings
SD-07 Certificates
Welders procedures and qualifications (metal and PE)
Pipe coating materials and application procedures
SD-10 Operation and Maintenance Data
Gas distribution system and equipment operation, Data package 4; G
Gas distribution system maintenance, Data package 4; G
Gas distribution equipment maintenance, Data Package 3; G
Submit operation and maintenance data in accordance with Section
01781 OPERATION AND MAINTENANCE DATA, in three separate packages.
SECTION 02551N
Page 9