Functional Performance Test Checklist - Centrifugal Chiller
For Chiller:
[_____]
1. Functional Performance Test: Contractor shall demonstrate operation of
chilled water system as per specifications including the following: Start
building air handler to provide load for chiller. Activate controls system
chiller start sequence as follows:
a.
Time of day startup program initiates chiller start:
____________
b. Start condenser water pump and establish condenser water flow.
Verify chiller condenser water proof-of-flow switch operation.
___________
c. Start chilled water pump and establish chilled water flow. Verify
chiller chilled water proof-of-flow switch operation.
____________________
d.
__________
e. Verify chiller senses chilled water temperature above set point and
__________________________________
f.
Verify functioning of "soft start" sequence.
_____________________
system. Verify chiller shutdown sequence is initiated and accomplished after
load is removed.
_______________________
Verify condenser water pump, cooling tower, and chiller restart sequence.
_____________________________________________________________________________
2. Certification: We the undersigned have witnessed the above functional
performance tests and certify that the item tested has met the performance
requirements in this section of the specifications.
Signature and Date
Contractor's Chief Quality Control Representative
_____________________________
Contractor's Mechanical Representative
_____________________________
Contractor's Electrical Representative
_____________________________
Contractor's Testing, Adjusting and Balancing Representative
_____________________________
Contractor's Controls Representative
_____________________________
Contracting Officer's Representative
_____________________________
Using Agency's Representative
_____________________________
SECTION 15995A