Quantcast Pre-commissioning Checklist - Pumps

 
  
 
Pre-commissioning Checklist - Pumps
For Pump:
[_____]
Checklist Item
Q
M
E
T
C
D
O
U
Installation
a.
Pumps grouted in place.
___ ___
X
X
X
___ ___ ___
b.
Pump vibration isolation devices
functional.
___ ___
X
X
X
___ ___ ___
c.
Pump/motor coupling alignment verified.
___ ___
X
X
X
___ ___ ___
d.
Piping system installed.
___ ___
X
X
X
___ ___ ___
e.
Piping system pressure tested.
___ ___
X
X
X
___ ___ ___
f.
Pump not leaking.
___ ___
X
X
X
___ ___ ___
g.
Field assembled couplings aligned to
meet manufacturer's prescribed tolerances.______
X
X
X
___ ___ ___
Electrical
a.
Power available to pump disconnect.
___ ___ ___
X
X
___ ___ ___
b.
Pump rotation verified.
___ ___ ___
X
X
___ ___ ___
c.
Control system interlocks functional.
___ ___ ___
X
___ ___ ___ ___
d.
Verify that power disconnect is located
within sight of the unit it controls.
___ ___ ___
X
___ ___ ___ ___
Testing, Adjusting, and Balancing (TAB)
a.
Pressure/temperature gauges installed.
___ ___
X
___
X
___ ___ ___
b.
Piping system cleaned.
___ ___
X
X
X
___ ___ ___
c.
Chemical water treatment complete.
___ ___
X
X
X
___ ___ ___
d.
Water balance complete.
___ ___
X
___
X
___ ___ ___
e.
Water balance with design maximum flow.
___ ___
X
___
X
___ ___ ___
f.
TAB Report submitted.
___ ___
X
___
X
___ ___ ___
SECTION 15995A
Page 15


 


Privacy Statement - Copyright Information. - Contact Us

comments powered by Disqus

Integrated Publishing, Inc.
9438 US Hwy 19N #311 Port Richey, FL 34668

Phone For Parts Inquiries: (727) 755-3260
Google +